Skip to content
Gridcensus

East 7th Street Peninsula - North (De1128)-2604400032; 2604400022

Industrial

Cumberland, New Jersey · PJM

DC Readiness
49.2
Fair / 100

East 7th Street Peninsula - North (De1128)-2604400032; 2604400022 is an industrial datacenter candidate site in Cumberland, New Jersey, interconnecting through PJM. It screens at 49.2/100 DC Readiness and a 2.7 yrs average interconnection-queue wait.

Power & interconnection

UtilityATLANTIC CITY ELECTRIC COinvestor ownedmoderate to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookConstrained
≈ 5.1 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionPJM
Queue depth720
Avg queue wait2.7 yrs
Recent queue wait5.1 yrs
Completion rate22%
Withdrawal rate78%

Connectivity

Nearest IXPIPR Wilmington CCC
IXP distance24.3 mi
Fiber providers4
Fiber coverage46.2%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterIPR Wilmington CCC
DC distance24.3 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.15¢/kWh
Industrial electricity9.53¢/kWh
Cooling degree days1,000
Heating degree days4,900
Land price / acre$11,056

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track East 7th Street Peninsula - North (De1128)-2604400032; 2604400022

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
40
Fiber connectivity12%
65
Energy cost10%
50
Water risk7%
84
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
30
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Cumberland, ranked by DC Readiness.

Sites near East 7th Street Peninsula - North (De1128)-2604400032; 2604400022
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN132614Substation-Adjacent230 kV300 MW2.7 yrs58.4
EC Near Howard DownGreenfield——2.7 yrs57.8
OZ CumberlandGreenfield——2.7 yrs56.9
Carlls CornerBrownfield—84 MW2.7 yrs56.0
EC Near Carlls CornerGreenfield——2.7 yrs55.3
SHERMAN STATIONSubstation-Adjacent138 kV100 MW2.7 yrs55.2
EC Near Howard DownGreenfield——2.7 yrs55.2
LINCOLN STATIONSubstation-Adjacent138 kV100 MW2.7 yrs55.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for East 7th Street Peninsula - North (De1128)-2604400032; 2604400022, Cumberland is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.