Datacenter Sites in Wheatland County, Montana
Wheatland County has 33 scored datacenter candidate sites averaging 58.9/100 DC Readiness, with a catalogued aggregate of 8,600 MW. FEMA rates local natural-hazard risk as "Very Low". The county has a datacenter tax incentive on record.
33
Candidate sites
58.9/100
Avg DC Readiness
8,600 MW
Catalogued capacity
theoretical aggregate
Very Low
Hazard rating
Site-selection context for Wheatland County
Yesproperty_tax_abatement
Datacenter tax incentive
8.42¢/kWh
Commercial electricity
8.61¢/kWh
Industrial electricity
3
Fiber providers
Medium-High
Water stress
$1,197
Land price / acre
400
Cooling degree days
7,600
Heating degree days
42°F
Mean annual temp
Incentive detail: New/expanding industry tax abatement available for DC construction.
By site type
Top datacenter sites in Wheatland County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| JUDITH GAP WIND ENERGY CENTER | Substation-Adjacent | 230 kV | 300 MW | 1.1 yrs | 74.5 |
| JUDITH GAP WIND FARM | Substation-Adjacent | 230 kV | 300 MW | 1.1 yrs | 74.3 |
| JUDITH GAP | Substation-Adjacent | 230 kV | 300 MW | 1.1 yrs | 74.3 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 71.5 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 71.2 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 70.9 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 70.5 |
| TAP205596 | Substation-Adjacent | 115 kV | 100 MW | 1.1 yrs | 69.9 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 69.7 |
| Greenfield (JUDITH GAP - UNKNOWN206326) | Greenfield | 230 kV | 300 MW | 1.1 yrs | 68.4 |
| Greenfield (BROADVIEW - JUDITH GAP WIND FA) | Greenfield | 230 kV | 300 MW | 1.1 yrs | 67.9 |
| Greenfield (JUDITH GAP - UNKNOWN206326) | Greenfield | 230 kV | 300 MW | 1.1 yrs | 67.8 |
| Greenfield (BROADVIEW - GARRISON) | Greenfield | 500 kV | 1,000 MW | 1.1 yrs | 67.5 |
| UNKNOWN204179 | Substation-Adjacent | 115 kV | 100 MW | 1.1 yrs | 67.3 |
| Greenfield (BROADVIEW - JUDITH GAP WIND FA) | Greenfield | 230 kV | 300 MW | 1.1 yrs | 67.0 |
| GORDON BUTTE WIND LLC | Substation-Adjacent | 100 kV | 50 MW | 1.1 yrs | 66.1 |
| TAP204196 | Substation-Adjacent | 100 kV | 50 MW | 1.1 yrs | 65.1 |
| Greenfield (UNKNOWN202126 - UNKNOWN204179) | Greenfield | 115 kV | 100 MW | 1.1 yrs | 63.6 |
| OZ Wheatland | Greenfield | — | — | 1.1 yrs | 59.4 |
| Greenfield (UNKNOWN202126 - UNKNOWN204179) | Greenfield | 115 kV | 100 MW | 1.1 yrs | 59.2 |
| Mine Site | Former Mine | — | — | — | 45.0 |
| Mine Site | Former Mine | — | — | — | 45.0 |
| Harlowton Roundhouse | Industrial | — | — | — | 45.0 |
| Mine Site | Former Mine | — | — | — | 45.0 |
| Bob's Chevron | Industrial | — | — | — | 45.0 |
Wheatland County datacenter FAQ
- How many datacenter sites are in Wheatland County?
- 33 scored datacenter candidate sites, averaging 58.9/100 DC Readiness.
- Does Wheatland County offer datacenter tax incentives?
- New/expanding industry tax abatement available for DC construction.
- What is the natural-hazard risk in Wheatland County?
- FEMA's National Risk Index rates Wheatland County as "Very Low" (score 12).
- What are industrial electricity rates in Wheatland County?
- Average industrial electricity is 8.61¢/kWh and commercial is 8.42¢/kWh in Wheatland County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Wheatland County, Montana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.