Datacenter Sites in Ralls County, Missouri
Ralls County has 21 scored datacenter candidate sites averaging 58.6/100 DC Readiness, with a catalogued aggregate of 3,800 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
21
Candidate sites
58.6/100
Avg DC Readiness
3,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Ralls County
Yessales_tax_exemption
Datacenter tax incentive
10.32¢/kWh
Commercial electricity
7.86¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$5,816
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp
Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.
By site type
Top datacenter sites in Ralls County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| AUDRAIN | Substation-Adjacent | 345 kV | 600 MW | 2.8 yrs | 60.7 |
| EC Coal Ralls County | Greenfield | — | — | 1.4 yrs | 59.0 |
| EC Coal Ralls County | Greenfield | — | — | 1.4 yrs | 58.5 |
| UNKNOWN117838 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.4 |
| TAP140522 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.4 |
| UNKNOWN120975 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.4 |
| UNKNOWN120842 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.4 |
| Greenfield (TAP140530 - TAP140541) | Greenfield | 345 kV | 600 MW | 2.8 yrs | 54.4 |
| TAP140521 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117792 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| TAP140533 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117738 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117737 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117165 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117833 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN117948 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 52.0 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 52.0 |
| UNKNOWN117960 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 51.6 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.3 |
| UNKNOWN117171 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 51.2 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.1 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 50.9 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 50.7 |
Ralls County datacenter FAQ
- How many datacenter sites are in Ralls County?
- 21 scored datacenter candidate sites, averaging 58.6/100 DC Readiness.
- Does Ralls County offer datacenter tax incentives?
- Qualified data center sales tax exemption (2019 law); state income tax credits.
- What is the natural-hazard risk in Ralls County?
- FEMA's National Risk Index rates Ralls County as "Relatively High" (score 38).
- What are industrial electricity rates in Ralls County?
- Average industrial electricity is 7.86¢/kWh and commercial is 10.32¢/kWh in Ralls County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Ralls County, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.