Skip to content
Gridcensus

UNKNOWN155799

Substation-Adjacent

Howell County, Missouri · MISO

DC Readiness
51.2
Fair / 100

UNKNOWN155799 is a substation-adjacent datacenter candidate site in Howell County, Missouri, interconnecting through MISO. It screens at 51.2/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN155799
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityHOWELL-OREGON ELEC COOP, INCcooperativefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth52
Avg queue wait2.8 yrs

Connectivity

Nearest IXPBluebird Underground Data Center
IXP distance79.2 mi
Fiber providers5
Fiber coverage27.4%

Site characteristics

Land contactHowell County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterBluebird Underground Data Center
DC distance79.2 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.00¢/kWh
Industrial electricity9.21¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$2,894

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN155799

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
45
Fiber connectivity12%
53
Energy cost10%
50
Water risk7%
88
Natural hazard6%
62
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
50

Nearby comparable sites

Other scored datacenter candidate sites in Howell County, ranked by DC Readiness.

Sites near UNKNOWN155799
SiteTypeVoltageCapacityQueue waitScore
OZ HowellGreenfield——1.4 yrs57.0
OZ HowellGreenfield——1.4 yrs55.3
UNKNOWN117958Substation-Adjacent161 kV100 MW2.8 yrs54.5
UNKNOWN117955Substation-Adjacent161 kV100 MW2.8 yrs54.3
TAP155795Substation-Adjacent69 kV50 MW2.8 yrs51.8
UNKNOWN122567Substation-Adjacent69 kV50 MW2.8 yrs51.8
UNKNOWN157454Substation-Adjacent69 kV50 MW2.8 yrs51.8
UNKNOWN122568Substation-Adjacent69 kV50 MW2.8 yrs51.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen