Datacenter Sites in Grundy, Missouri
Grundy has 17 scored datacenter candidate sites averaging 56.3/100 DC Readiness, with a catalogued aggregate of 304 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
17
Candidate sites
56.3/100
Avg DC Readiness
304 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Grundy
Yessales_tax_exemption
Datacenter tax incentive
10.11¢/kWh
Commercial electricity
6.94¢/kWh
Industrial electricity
2
Fiber providers
Low
Water stress
$4,305
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp
Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.
By site type
Top datacenter sites in Grundy
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Trenton Diesel | Brownfield | — | 4 MW | 1.4 yrs | 61.0 |
| Greenfield (UNKNOWN117364 - UNKNOWN117493) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 60.6 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 59.3 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 59.1 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 59.0 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 58.6 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 58.2 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 57.9 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 57.8 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 56.9 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 56.5 |
| Greenfield (UNKNOWN117364 - UNKNOWN117493) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 55.8 |
| Greenfield (UNKNOWN117364 - UNKNOWN117493) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 55.5 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 53.7 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 53.1 |
| EC Near Trenton Diesel | Greenfield | — | — | 1.4 yrs | 50.6 |
| Mine Site | Former Mine | — | — | — | 43.3 |
Grundy datacenter FAQ
- How many datacenter sites are in Grundy?
- 17 scored datacenter candidate sites, averaging 56.3/100 DC Readiness.
- Does Grundy offer datacenter tax incentives?
- Qualified data center sales tax exemption (2019 law); state income tax credits.
- What is the natural-hazard risk in Grundy?
- FEMA's National Risk Index rates Grundy as "Relatively High" (score 38).
- What are industrial electricity rates in Grundy?
- Average industrial electricity is 6.94¢/kWh and commercial is 10.11¢/kWh in Grundy.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Grundy, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.