Union Pacific Railroad (UPRR)

Industrial

Buchanan County, Missouri · MISO

DC Readiness
50.7
Fair / 100

Union Pacific Railroad (UPRR) is an industrial datacenter candidate site in Buchanan County, Missouri, interconnecting through MISO. It screens at 50.7/100 DC Readiness and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityEVERGY MISSOURI WESTinvestor ownedfavorable to large load · terms ≥ 75 MWLarge Load Power Service (LLPS, ≥75 MW) · 80% min take · 12 yr

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth52
Avg queue wait2.8 yrs

Connectivity

Nearest IXPLincoln Rackhouse Kansas City
IXP distance33.5 mi
Fiber providers6
Fiber coverage93.6%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterDatacenter 00195169261
DC distance32.9 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.37¢/kWh
Industrial electricity8.74¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$5,382

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Union Pacific Railroad (UPRR)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
45
Fiber connectivity12%
75
Energy cost10%
50
Water risk7%
88
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
50

Nearby comparable sites

Other scored datacenter candidate sites in Buchanan County, ranked by DC Readiness.

Sites near Union Pacific Railroad (UPRR)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN162404Substation-Adjacent345 kV600 MW2.8 yrs63.6
OZ BuchananGreenfield——1.4 yrs61.0
UNKNOWN117504Substation-Adjacent161 kV100 MW2.8 yrs58.3
UNKNOWN117118Substation-Adjacent161 kV100 MW2.8 yrs58.2
UNKNOWN120835Substation-Adjacent161 kV100 MW2.8 yrs58.2
UNKNOWN120834Substation-Adjacent161 kV100 MW2.8 yrs57.4
UNKNOWN117446Substation-Adjacent161 kV100 MW2.8 yrs57.2
UNKNOWN117454Substation-Adjacent161 kV100 MW2.8 yrs57.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Union Pacific Railroad (UPRR), Buchanan County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.