Westboro School (former)

Industrial

Atchison County, Missouri · MISO

DC Readiness
41.2
Fair / 100

Westboro School (former) is a industrial datacenter candidate site in Atchison County, Missouri, interconnecting through MISO. It screens at 41.2/100 DC Readiness.

Power & interconnection

Speed to power

ISO / RTO regionMISO
Queue depth34

Connectivity

Nearest IXPTierPoint Omaha - Bellevue
IXP distance54.4 mi

Site characteristics

Site typeIndustrial

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score50/100

Location context

Nearest datacenterGoogle
DC distance50.3 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.57¢/kWh
Industrial electricity6.88¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$6,221

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
40
Fiber connectivity12%
43
Energy cost10%
50
Water risk8%
50
Natural hazard8%
50
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Atchison County, ranked by DC Readiness.

Sites near Westboro School (former)
SiteTypeVoltageCapacityQueue waitScore
COOPERSubstation-Adjacent345 kV600 MW3.5 yrs68.5
BOONEVILLESubstation-Adjacent345 kV600 MW3.5 yrs66.3
Greenfield (COOPER - ATCHISON)Greenfield345 kV600 MW3.5 yrs64.2
Greenfield (COOPER - FAIRPORT)Greenfield345 kV600 MW3.5 yrs63.1
Greenfield (COOPER - FAIRPORT)Greenfield345 kV600 MW3.5 yrs62.9
Greenfield (COOPER - ATCHISON)Greenfield345 kV600 MW3.5 yrs62.5
Greenfield (COOPER - FAIRPORT)Greenfield345 kV600 MW3.5 yrs62.0
Greenfield (ATCHISON - BOONEVILLE)Greenfield345 kV600 MW3.5 yrs61.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.