LAWRENCE, Mississippi · MISO

DC Readiness
52.9
Fair / 100

TAP142760 is a substation-adjacent datacenter candidate site in LAWRENCE, Mississippi, interconnecting through MISO. It screens at 52.9/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP142760
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
UtilityENTERGY MISSISSIPPI LLCinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth59
Avg queue wait2.8 yrs

Connectivity

Nearest IXPEdgeConneX New Orleans (EDCSLI01)
IXP distance92.1 mi
Fiber providers7
Fiber coverage36.1%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score55/100

Location context

Nearest datacenterAmazon Web Services
DC distance57.3 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.17¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$3,498

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP142760

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
33
Fiber connectivity12%
59
Energy cost10%
50
Water risk7%
90
Natural hazard6%
55
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
50
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
5

Nearby comparable sites

Other scored datacenter candidate sites in LAWRENCE, ranked by DC Readiness.

Sites near TAP142760
SiteTypeVoltageCapacityQueue waitScore
EC FFE Lawrence CountyGreenfield——1.4 yrs53.3
UNKNOWN110163Substation-Adjacent115 kV100 MW2.8 yrs53.1
UNKNOWN110162Substation-Adjacent115 kV100 MW2.8 yrs53.1
UNKNOWN109885Substation-Adjacent115 kV100 MW2.8 yrs52.7
MONTICELLO HARDWOOD, INC. (WOOD PRESERVATION)Manufacturing——3.5 yrs49.6
ATLAS MFG. CO., INC. (NOT AVAILABLE)Manufacturing——3.5 yrs49.5
MILES & SONS, INC., JOE N. (SAWMILLS)Manufacturing——3.5 yrs49.3
LEE'S PIGSKIN CO., INC. (OTHER SNACK FOOD MANUFACTURING)Manufacturing——3.5 yrs48.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for TAP142760, LAWRENCE is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.