Baltimore, Maryland · PJM

DC Readiness
59.5
Good / 100

EAST TOWSON is a substation-adjacent datacenter candidate site in Baltimore, Maryland, interconnecting through PJM. It screens at 59.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationEAST TOWSON
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth308
Avg queue wait3.8 yrs

Connectivity

Nearest IXPLumen Baltimore
IXP distance7.5 mi
Fiber providers10
Fiber coverage93.3%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterAiNET One Market Center
DC distance7.5 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_credits)
Commercial electricity9.93¢/kWh
Industrial electricity8.79¢/kWh
Cooling degree days1,300
Heating degree days4,400
Land price / acre$13,587

Incentive detail: Enterprise Zone property tax credits; personal property tax credits on DC equipment.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
30
Fiber connectivity12%
87
Energy cost10%
50
Water risk8%
84
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
37
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Baltimore, ranked by DC Readiness.

Sites near EAST TOWSON
SiteTypeVoltageCapacityQueue waitScore
EC Near Riverside (MD)Greenfield3.5 yrs64.4
OZ BaltimoreGreenfield3.5 yrs64.2
EC Near Notch CliffGreenfield3.5 yrs63.2
EC Near Notch CliffGreenfield3.5 yrs62.9
TAP155935Substation-Adjacent115 kV100 MW3.8 yrs61.7
EC Near Notch CliffGreenfield3.5 yrs61.7
UNKNOWN123099Substation-Adjacent115 kV100 MW3.8 yrs61.6
UNKNOWN123100Substation-Adjacent115 kV100 MW3.8 yrs61.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EAST TOWSON, Baltimore. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.