UNKNOWN112533 is a substation-adjacent datacenter candidate site in Livingston County, Louisiana, interconnecting through MISO. It screens at 58.9/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN112533
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityENTERGY LOUISIANA LLCinvestor ownedfavorable to large load · terms ≥ 50 MWLarge-load contracts with dedicated generation (Meta Richland Parish) · 15 yr

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth120
Avg queue wait2.8 yrs

Connectivity

Nearest IXPDartPoints Baton Rouge, LA - BTR1
IXP distance32.3 mi
Fiber providers5
Fiber coverage69.4%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score42/100

Location context

Nearest datacenterVenyu BTR1
DC distance32.3 mi
County hazard (FEMA NRI)Very High (58)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.55¢/kWh
Industrial electricity10.02¢/kWh
Cooling degree days2,700
Heating degree days1,700
Land price / acre$6,940

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN112533

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
48
Fiber connectivity12%
67
Energy cost10%
50
Water risk7%
88
Natural hazard6%
42
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Livingston County, ranked by DC Readiness.

Sites near UNKNOWN112533
SiteTypeVoltageCapacityQueue waitScore
COLYSubstation-Adjacent500 kV1,000 MW2.8 yrs66.8
OZ LivingstonGreenfield——1.4 yrs59.1
Greenfield (UNKNOWN112526 - UNKNOWN112533)Greenfield230 kV300 MW2.8 yrs53.3
4-H Club Road PropertyIndustrial——2.8 yrs52.4
Mine SiteFormer Mine——2.8 yrs52.1
Mine SiteFormer Mine——2.8 yrs52.0
Mine SiteFormer Mine——2.8 yrs52.0
Mine SiteFormer Mine——2.8 yrs51.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.