Skip to content
Gridcensus

Grundy County, Iowa · MISO

DC Readiness
58.0
Good / 100

TAP136964 is a substation-adjacent datacenter candidate site in Grundy County, Iowa, interconnecting through MISO. It screens at 58.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP136964
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW

Speed to power

ISO / RTO regionMISO
Queue depth23
Avg queue wait2.8 yrs

Connectivity

Nearest IXPSFN IA-IowaFalls
IXP distance21.3 mi
Fiber providers9
Fiber coverage66.9%

Site characteristics

Risk & environment

Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterSFN IA-IowaFalls
DC distance21.3 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.29¢/kWh
Industrial electricity7.40¢/kWh
Cooling degree days900
Heating degree days6,500
Land price / acre$12,121

Incentive detail: Sales tax exemption on DC equipment for $1M+ investments; property tax phase-in for new construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 4 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power15%
46
Fiber connectivity12%
54
Energy cost10%
50
Water risk8%
88
Natural hazard8%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
39
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Grundy County, ranked by DC Readiness.

Sites near TAP136964
SiteTypeVoltageCapacityQueue waitScore
BUTLERSubstation-Adjacent161 kV100 MW2.8 yrs58.8
Mine SiteFormer Mine2.8 yrs54.4
Tyler DudaIndustrial2.8 yrs53.2
Greenfield (UNKNOWN130756 - MARSHALLTOWN)Greenfield161 kV100 MW2.8 yrs50.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP136964, Grundy County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.