LA PORTE has 173 scored datacenter candidate sites averaging 55.7/100 DC Readiness, with a catalogued aggregate of 7,600 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

173
Candidate sites
55.7/100
Avg DC Readiness
7,600 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in LA PORTE

Site-selection context for LA PORTE

Yessales_tax_exemption
Datacenter tax incentive
15.54¢/kWh
Commercial electricity
8.12¢/kWh
Industrial electricity
8
Fiber providers
Low
Water stress
$5,056
Land price / acre
1,000
Cooling degree days
5,500
Heating degree days
52°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

By site type

Top datacenter sites in LA PORTE

Top datacenter sites in LA PORTE
SiteTypeVoltageCapacityQueue waitScore
EC Near St Joseph Energy CenterGreenfield3.0 yrs62.7
UNKNOWN122727Substation-Adjacent345 kV600 MW3.8 yrs62.0
EC Near St Joseph Energy CenterGreenfield3.0 yrs61.1
EC Near Michigan CityGreenfield3.0 yrs60.2
EC Near St Joseph Energy CenterGreenfield3.0 yrs60.2
OZ LaPorteGreenfield3.0 yrs58.8
UNKNOWN122736Substation-Adjacent138 kV100 MW3.8 yrs56.7
EC Coal LaPorte CountyGreenfield3.0 yrs56.7
TAP139935Substation-Adjacent138 kV100 MW3.8 yrs56.6
TAP155830Substation-Adjacent138 kV100 MW3.8 yrs56.3
Greenfield (OLIVE - REYNOLDS)Greenfield345 kV600 MW8.2 yrs55.7
UNKNOWN122735Substation-Adjacent138 kV100 MW3.8 yrs55.1
PLANT LIFE SOILS, INC. (FERTILIZER (MIXING ONLY) MANUFACTURING)Manufacturing3.5 yrs54.9
OZ LaPorteGreenfield3.0 yrs54.9
WEISS PRESTAIN (ALL OTHER PLASTICS PRODUCT MANUFACTURING)Manufacturing3.5 yrs54.9
O'TECH CORP. (NOT AVAILABLE)Manufacturing3.5 yrs54.8
GRIMM MOLD & DIE CO., INC. (INDUSTRIAL MOLD MANUFACTURING)Manufacturing3.5 yrs54.8
MASTER ROLL MFG. (MECHANICAL POWER TRANSMISSION EQUIPMENT MANUFACTURING)Manufacturing3.5 yrs54.7
ROTATION DYNAMICS, INC. (PRINTING MACHINERY AND EQUIPMENT MANUFACTURING)Manufacturing3.5 yrs54.7
ALPHA BAKING CO., INC. (COMMERCIAL BAKERIES)Manufacturing3.5 yrs54.7
EASTON CONTROLS, INC. (NOT AVAILABLE)Manufacturing3.5 yrs54.7
EMC (ALUMINUM DIE-CASTING FOUNDRIES)Manufacturing3.5 yrs54.7
STEWART SUPERIOR CORP. (MARKING DEVICE MANUFACTURING)Manufacturing3.5 yrs54.7
DWYER INSTRUMENTS, INC. (METAL STAMPING)Manufacturing3.5 yrs54.7
HY-TEK HOSE & COUPLING (RUBBER AND PLASTICS HOSES AND BELTING MANUFACTURING)Manufacturing3.5 yrs54.7

LA PORTE datacenter FAQ

How many datacenter sites are in LA PORTE?
173 scored datacenter candidate sites, averaging 55.7/100 DC Readiness.
Does LA PORTE offer datacenter tax incentives?
Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.
What is the natural-hazard risk in LA PORTE?
FEMA's National Risk Index rates LA PORTE as "Relatively Moderate" (score 32).
What are industrial electricity rates in LA PORTE?
Average industrial electricity is 8.12¢/kWh and commercial is 15.54¢/kWh in LA PORTE.