Datacenter Sites in DE KALB, Indiana
DE KALB has 105 scored datacenter candidate sites averaging 54.6/100 DC Readiness, with a catalogued aggregate of 3,800 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
105
Candidate sites
54.6/100
Avg DC Readiness
3,800 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for DE KALB
Yessales_tax_exemption
Datacenter tax incentive
13.31¢/kWh
Commercial electricity
8.75¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$8,646
Land price / acre
1,000
Cooling degree days
5,500
Heating degree days
52°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.
By site type
Top datacenter sites in DE KALB
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| SOUTH BUTLER | Substation-Adjacent | 345 kV | 600 MW | 3.0 yrs | 73.8 |
| TAP160235 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.3 |
| Greenfield (HIPLE - ROBISON PARK (345 KV)) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 67.8 |
| AUBURN (69KV) | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 67.6 |
| Greenfield (HIPLE - ROBISON PARK (345 KV)) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 67.5 |
| UNKNOWN160238 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 67.2 |
| TAP160236 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 67.1 |
| TAP173179 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 67.0 |
| TAP173179 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 66.8 |
| BUTLER | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.4 |
| AUBURN (138KV) | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 63.7 |
| TAP155895 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 63.7 |
| Greenfield (COLLINGWOOD - SOUTH BUTLER) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 62.6 |
| COUNTY LINE | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 62.1 |
| UNKNOWN123169 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 61.0 |
| Greenfield (TAP155895 - UNKNOWN160238) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 60.9 |
| OZ DeKalb | Greenfield | — | — | 3.0 yrs | 60.6 |
| WINDAMATIC SYSTEMS, INC. (SPECIAL DIE AND TOOL, DIE SET, JIG, AND FIXTURE MANUFACTURING) | Manufacturing | — | — | — | 56.0 |
| WAYNE MFG. CORP. (METAL STAMPING) | Manufacturing | — | — | — | 55.7 |
| WAYNE TOOL & DESIGN, INC. (SPECIAL DIE AND TOOL, DIE SET, JIG, AND FIXTURE MANUFACTURING) | Manufacturing | — | — | — | 55.7 |
| X-Y TOOL & DIE, INC. (NOT AVAILABLE) | Manufacturing | — | — | — | 55.7 |
| Greenfield (SOUTH HICKSVILLE - GRABILL) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 54.8 |
| ELECTRIC MOTORS & SPECIALTIES, INC. (MOTOR AND GENERATOR MANUFACTURING) | Manufacturing | — | — | — | 54.8 |
| Greenfield (BUTLER - TAP173179) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 54.5 |
| MAVERICK MOLDING, INC. (ALL OTHER RUBBER PRODUCT MANUFACTURING) | Manufacturing | — | — | — | 53.9 |
DE KALB datacenter FAQ
- How many datacenter sites are in DE KALB?
- 105 scored datacenter candidate sites, averaging 54.6/100 DC Readiness.
- Does DE KALB offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.
- What is the natural-hazard risk in DE KALB?
- FEMA's National Risk Index rates DE KALB as "Relatively Moderate" (score 32).
- What are industrial electricity rates in DE KALB?
- Average industrial electricity is 8.75¢/kWh and commercial is 13.31¢/kWh in DE KALB.
Dataset updated . Screening estimates derived from public data sources.