UNKNOWN122046

Substation-Adjacent

Jersey County, Illinois · PJM

DC Readiness
59.0
Good / 100

UNKNOWN122046 is a substation-adjacent datacenter candidate site in Jersey County, Illinois, interconnecting through PJM. It screens at 59.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN122046
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilitySOUTHWESTERN ELECTRIC COOP INC - (IL)cooperativemoderate to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth393
Avg queue wait3.8 yrs

Connectivity

Nearest IXPTierPoint St. Louis – Millpark
IXP distance30.0 mi
Fiber providers5
Fiber coverage56.5%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterTierPoint St. Louis – Millpark
DC distance30.0 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.97¢/kWh
Industrial electricity3.67¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$8,366

Regulatory climate

Restrictivestate posture · as of 2026-08

New-DC state tax exemptions suspended for 2 years (from Jul 2026).

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Get alerts

Track UNKNOWN122046

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
49
Fiber connectivity12%
66
Energy cost10%
50
Water risk7%
88
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
70

Nearby comparable sites

Other scored datacenter candidate sites in Jersey County, ranked by DC Readiness.

Sites near UNKNOWN122046
SiteTypeVoltageCapacityQueue waitScore
SIOUXSubstation-Adjacent345 kV600 MW2.8 yrs63.1
UNKNOWN121190Substation-Adjacent138 kV100 MW2.8 yrs57.3
Greenfield (O'FALLON RENEWABLE ENERGY CENT)Greenfield345 kV600 MW2.8 yrs56.6
OZ JerseyGreenfield——4.6 yrs53.7
Mine SiteFormer Mine——3.8 yrs52.2
Greenfield (SIOUX - TAP167219)Greenfield138 kV100 MW2.8 yrs51.8
Mine SiteFormer Mine——3.8 yrs51.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for UNKNOWN122046, Jersey County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.