Skip to content
Gridcensus

Crawford County, Illinois · PJM

DC Readiness
53.7
Fair / 100

HUTSONVILLE is a substation-adjacent datacenter candidate site in Crawford County, Illinois, interconnecting through PJM. It screens at 53.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHUTSONVILLE
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth393
Avg queue wait3.8 yrs

Connectivity

Nearest IXPIndiana University Data Center
IXP distance62.2 mi
Fiber providers6
Fiber coverage64.6%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterIU Data Center
DC distance62.2 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.28¢/kWh
Industrial electricity7.14¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$6,710

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
49
Fiber connectivity12%
35
Energy cost10%
50
Water risk8%
88
Natural hazard8%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
70

Nearby comparable sites

Other scored datacenter candidate sites in Crawford County, ranked by DC Readiness.

Sites near HUTSONVILLE
SiteTypeVoltageCapacityQueue waitScore
EC Coal Crawford CountyGreenfield4.6 yrs60.2
OZ CrawfordGreenfield4.6 yrs59.3
EC Coal Crawford CountyGreenfield4.6 yrs57.9
EC Coal Crawford CountyGreenfield4.6 yrs57.6
EC Coal Crawford CountyGreenfield4.6 yrs56.3
EC Coal Crawford CountyGreenfield4.6 yrs56.2
TAP169377Substation-Adjacent138 kV100 MW3.8 yrs53.7
UNKNOWN157064Substation-Adjacent138 kV100 MW3.8 yrs53.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for HUTSONVILLE, Crawford County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.