UNKNOWN120311

Substation-Adjacent

Hardee, Florida · SERC

DC Readiness
66.1
Good / 100

UNKNOWN120311 is a substation-adjacent datacenter candidate site in Hardee, Florida, interconnecting through SERC. It screens at 66.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN120311
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityDUKE ENERGY FLORIDA, LLCinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPLawton Information Services, LLC
IXP distance15.7 mi
Fiber providers5
Fiber coverage20.9%

Site characteristics

Former usegas
Existing capacity1,859 MW

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterLawton Information Services, LLC
DC distance15.7 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.13¢/kWh
Industrial electricity15.01¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$6,616

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN120311

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
84
Fiber connectivity12%
68
Energy cost10%
50
Water risk7%
76
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Hardee, ranked by DC Readiness.

Sites near UNKNOWN120311
SiteTypeVoltageCapacityQueue waitScore
Brownfield SiteBrownfield—1,560 MW3.6 yrs67.0
UNKNOWN127705Substation-Adjacent230 kV300 MW1.0 yrs65.5
UNKNOWN153224Substation-Adjacent230 kV300 MW1.0 yrs63.2
VANDOLAHSubstation-Adjacent230 kV300 MW1.0 yrs62.6
EC Near UnknownGreenfield——3.6 yrs62.1
EC Near Midulla Generating StationGreenfield——3.6 yrs61.9
EC Near UnknownGreenfield——3.6 yrs61.0
EC Near UnknownGreenfield——3.6 yrs60.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN120311, Hardee. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.