Skip to content
Gridcensus

Mine Site

Former Mine

Glades County, Florida · SERC

DC Readiness
51.4
Fair / 100

Mine Site is a former mine datacenter candidate site in Glades County, Florida, interconnecting through SERC. It screens at 51.4/100 DC Readiness and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

UtilityFLORIDA POWER & LIGHT COinvestor ownedfavorable to large load · terms ≥ 50 MWLarge Load Contract Service (LLCS, ≥50 MW) · 90% min take · 20 yr

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPSKYLINK DATA CENTERS
IXP distance52.5 mi
Fiber providers4
Fiber coverage46.5%

Site characteristics

Site typeFormer Mine
Land contactGlades County County Assessor
Former useMining: Nonmetal; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterSKYLINK DATA CENTERS
DC distance52.5 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity15.98¢/kWh
Industrial electricity11.17¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$4,623

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
73
Fiber connectivity12%
57
Energy cost10%
50
Water risk7%
76
Natural hazard6%
45
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Glades County, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
HICPOCHEESubstation-Adjacent138 kV100 MW1.0 yrs58.3
OZ GladesGreenfield——3.6 yrs55.6
Mine SiteFormer Mine——1.0 yrs52.1
A Duda & Sons PropertyIndustrial——1.0 yrs52.0
Mine SiteFormer Mine——1.0 yrs51.4
Former Glades Inn SiteIndustrial——1.0 yrs51.3
Former First Bank SiteIndustrial——1.0 yrs51.3
Avenue J PropertiesIndustrial——1.0 yrs51.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Mine Site, Glades County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.