UNKNOWN108485 is a substation-adjacent datacenter candidate site in DeSoto, Florida, interconnecting through SERC. It screens at 61.7/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN108485
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityFLORIDA POWER & LIGHT COinvestor ownedfavorable to large load · terms ≥ 50 MWLarge Load Contract Service (LLCS, ≥50 MW) · 90% min take · 20 yr

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPLawton Information Services, LLC
IXP distance56.6 mi
Fiber providers4
Fiber coverage36.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score45/100

Location context

Nearest datacenterLawton Information Services, LLC
DC distance56.6 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.17¢/kWh
Industrial electricity11.21¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$6,531

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN108485

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
73
Fiber connectivity12%
57
Energy cost10%
50
Water risk7%
76
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in DeSoto, ranked by DC Readiness.

Sites near UNKNOWN108485
SiteTypeVoltageCapacityQueue waitScore
WHIDDENSubstation-Adjacent230 kV300 MW1.0 yrs61.9
UNKNOWN120585Substation-Adjacent230 kV300 MW1.0 yrs61.6
OZ DeSotoGreenfield3.6 yrs56.0
Mine SiteFormer Mine1.0 yrs51.8
Arcadia Housing AuthorityIndustrial1.0 yrs51.8
OZ DeSotoGreenfield3.6 yrs51.4
Mine SiteFormer Mine1.0 yrs51.1
Mine SiteFormer Mine1.0 yrs50.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN108485, DeSoto. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.