Datacenter Sites in Union County, Arkansas

Union County has 42 scored datacenter candidate sites averaging 57.3/100 DC Readiness, with a catalogued aggregate of 14,200 MW. FEMA rates local natural-hazard risk as "Relatively High".

42
Candidate sites
57.3/100
Avg DC Readiness
14,200 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating

Site-selection context for Union County

No
Datacenter tax incentive
10.74¢/kWh
Commercial electricity
7.18¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$2,912
Land price / acre
1,900
Cooling degree days
3,400
Heating degree days
60°F
Mean annual temp

By site type

Top datacenter sites in Union County

Top datacenter sites in Union County
SiteTypeVoltageCapacityQueue waitScore
UNION POWER STATIONSubstation-Adjacent500 kV1,000 MW1.4 yrs70.9
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)Greenfield500 kV1,000 MW1.4 yrs64.3
Greenfield (UNKNOWN107970 - EL DORADO SUBS)Greenfield500 kV1,000 MW1.4 yrs64.2
Greenfield (UNKNOWN107970 - EL DORADO SUBS)Greenfield500 kV1,000 MW1.4 yrs63.9
Greenfield (UNKNOWN107970 - EL DORADO SUBS)Greenfield500 kV1,000 MW1.4 yrs63.9
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)Greenfield500 kV1,000 MW1.4 yrs63.6
Greenfield (EL DORADO SUBSTATION - STERLIN)Greenfield500 kV1,000 MW1.4 yrs63.0
Greenfield (EL DORADO SUBSTATION - STERLIN)Greenfield500 kV1,000 MW1.4 yrs62.8
UNKNOWN107831Substation-Adjacent115 kV100 MW1.4 yrs62.7
UNKNOWN107828Substation-Adjacent115 kV100 MW1.4 yrs62.1
UNKNOWN107833Substation-Adjacent115 kV100 MW1.4 yrs62.1
UNKNOWN107836Substation-Adjacent115 kV100 MW1.4 yrs62.1
UNKNOWN107829Substation-Adjacent115 kV100 MW1.4 yrs61.3
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)Greenfield500 kV1,000 MW1.4 yrs61.3
UNKNOWN116923Substation-Adjacent115 kV100 MW1.4 yrs60.5
Greenfield (EL DORADO SUBSTATION - STERLIN)Greenfield500 kV1,000 MW1.4 yrs60.3
UNKNOWN107838Substation-Adjacent115 kV100 MW1.4 yrs60.3
Greenfield (SAREPTA - EL DORADO SUBSTATION)Greenfield345 kV600 MW1.4 yrs59.6
TAP142049Substation-Adjacent115 kV100 MW1.4 yrs59.3
UNKNOWN121606Substation-Adjacent115 kV100 MW1.4 yrs59.3
Greenfield (SAREPTA - EL DORADO SUBSTATION)Greenfield345 kV600 MW1.4 yrs58.8
UNKNOWN107830Substation-Adjacent115 kV100 MW1.4 yrs58.0
UNKNOWN107843Substation-Adjacent115 kV100 MW1.4 yrs57.9
UNKNOWN107841Substation-Adjacent115 kV100 MW1.4 yrs57.9
UNKNOWN107839Substation-Adjacent115 kV100 MW1.4 yrs57.8

Union County datacenter FAQ

How many datacenter sites are in Union County?
42 scored datacenter candidate sites, averaging 57.3/100 DC Readiness.
Does Union County offer datacenter tax incentives?
No datacenter-specific tax incentive is on record for Union County in our dataset.
What is the natural-hazard risk in Union County?
FEMA's National Risk Index rates Union County as "Relatively High" (score 38).
What are industrial electricity rates in Union County?
Average industrial electricity is 7.18¢/kWh and commercial is 10.74¢/kWh in Union County.