Skip to content
Gridcensus

Logan County, Arkansas · MISO

DC Readiness
50.8
Fair / 100

BOONEVILLE is a substation-adjacent datacenter candidate site in Logan County, Arkansas, interconnecting through MISO. It screens at 50.8/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBOONEVILLE
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityARKANSAS VALLEY ELEC COOP CORPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth136
Avg queue wait2.8 yrs

Connectivity

Nearest IXPOzarksGo Fayetteville
IXP distance67.0 mi
Fiber providers4
Fiber coverage92.9%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterOzarksGo Fayetteville
DC distance67.0 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveNo
Commercial electricity10.80¢/kWh
Industrial electricity6.43¢/kWh
Cooling degree days1,900
Heating degree days3,400
Land price / acre$3,129

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track BOONEVILLE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
46
Fiber connectivity12%
61
Energy cost10%
50
Water risk7%
84
Natural hazard6%
62
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
30

Nearby comparable sites

Other scored datacenter candidate sites in Logan County, ranked by DC Readiness.

Sites near BOONEVILLE
SiteTypeVoltageCapacityQueue waitScore
OZ LoganGreenfield——1.4 yrs57.1
EC Coal Logan CountyGreenfield——1.4 yrs55.9
EC FFE Logan CountyGreenfield——1.4 yrs55.6
UNKNOWN117224Substation-Adjacent161 kV100 MW2.8 yrs55.3
SHORT MOUNTAINSubstation-Adjacent161 kV100 MW2.8 yrs55.2
BRANCHSubstation-Adjacent161 kV100 MW2.8 yrs55.1
RAZORBACKSubstation-Adjacent161 kV100 MW2.8 yrs54.7
TAP154324Substation-Adjacent161 kV100 MW2.8 yrs54.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for BOONEVILLE, Logan County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.