Skip to content
Gridcensus

Former Ever Corporation Building

Industrial

Jackson County, Arkansas · MISO

DC Readiness
46.6
Fair / 100

Former Ever Corporation Building is an industrial datacenter candidate site in Jackson County, Arkansas, interconnecting through MISO. It screens at 46.6/100 DC Readiness and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityENTERGY ARKANSAS LLCinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth136
Avg queue wait2.8 yrs

Connectivity

Nearest IXPARE-ON Forrest City
IXP distance49.9 mi
Fiber providers5
Fiber coverage83.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterSearcy Information Technologies
DC distance38.7 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveNo
Commercial electricity10.97¢/kWh
Industrial electricity9.69¢/kWh
Cooling degree days1,900
Heating degree days3,400
Land price / acre$4,007

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Former Ever Corporation Building

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
28
Fiber connectivity12%
73
Energy cost10%
50
Water risk7%
84
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
30

Nearby comparable sites

Other scored datacenter candidate sites in Jackson County, ranked by DC Readiness.

Sites near Former Ever Corporation Building
SiteTypeVoltageCapacityQueue waitScore
EC FFE Jackson CountyGreenfield——1.4 yrs55.2
UNKNOWN121322Substation-Adjacent161 kV100 MW2.8 yrs54.1
NEWPORT SUBSTATIONSubstation-Adjacent161 kV100 MW2.8 yrs53.3
UNKNOWN117330Substation-Adjacent161 kV100 MW2.8 yrs53.3
UNKNOWN117237Substation-Adjacent161 kV100 MW2.8 yrs53.3
UNKNOWN117331Substation-Adjacent161 kV100 MW2.8 yrs53.2
UNKNOWN108071Substation-Adjacent161 kV100 MW2.8 yrs53.1
UNKNOWN173582Substation-Adjacent161 kV100 MW2.8 yrs52.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Former Ever Corporation Building, Jackson County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.