DC Readiness
50.6
Fair / 100

AECC JONESBORO NORTH is a substation-adjacent datacenter candidate site in Greene County, Arkansas, interconnecting through MISO. It screens at 50.6/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationAECC JONESBORO NORTH
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW

Speed to power

ISO / RTO regionMISO
Queue depth101
Avg queue wait2.8 yrs

Connectivity

Nearest IXPARE-ON Forrest City
IXP distance65.7 mi
Fiber providers4
Fiber coverage99.9%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score62/100

Location context

Nearest datacenterxAI Memphis DC
DC distance64.2 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveNo
Commercial electricity12.15¢/kWh
Industrial electricity9.45¢/kWh
Cooling degree days1,900
Heating degree days3,400
Land price / acre$4,818

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power15%
39
Fiber connectivity12%
45
Energy cost10%
50
Water risk8%
84
Natural hazard8%
62
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
30

Nearby comparable sites

Other scored datacenter candidate sites in Greene County, ranked by DC Readiness.

Sites near AECC JONESBORO NORTH
SiteTypeVoltageCapacityQueue waitScore
EC Near ParagouldGreenfield1.4 yrs57.3
EC FFE Greene CountyGreenfield1.4 yrs57.0
EC Near ParagouldGreenfield1.4 yrs56.5
EC Near ParagouldGreenfield1.4 yrs55.8
EC Near ParagouldGreenfield1.4 yrs55.3
EC Near ParagouldGreenfield1.4 yrs55.0
EC Near ParagouldGreenfield1.4 yrs54.6
EC Near ParagouldGreenfield1.4 yrs54.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for AECC JONESBORO NORTH, Greene County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.