Skip to content
Gridcensus

Smuggler Cove Relay Station

Industrial

Prince of Wales-Hyder County, Alaska

DC Readiness
50.6
Fair / 100

Smuggler Cove Relay Station is an industrial datacenter candidate site in Prince of Wales-Hyder County, Alaska. It screens at 50.6/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

Avg queue wait3.5 yrs

Connectivity

Fiber providers2
Fiber coverage33.3%

Site characteristics

Site typeIndustrial

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score82/100

Location context

County hazard (FEMA NRI)Relatively Low (18)
DC tax incentiveNo
Commercial electricity31.31¢/kWh
Cooling degree days0
Heating degree days10,000
Land price / acre$20,972

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
47
Fiber connectivity12%
59
Energy cost10%
50
Water risk8%
96
Natural hazard8%
82
Buildability7%
50
Labor market4%
50
DC cluster4%
10
Land / acreage3%
53
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Prince of Wales-Hyder County, ranked by DC Readiness.

Sites near Smuggler Cove Relay Station
SiteTypeVoltageCapacityQueue waitScore
NDB DF ANNETTE ISLANDFederal Excess1.0 yrs54.8
NWS WSO UAIB ANNETTE AK SITE 1 INSTALLATIONFederal Excess1.0 yrs53.8
TONGASS NATIONAL FORESTFederal Excess1.0 yrs53.7
KLAWOCKFederal Excess1.0 yrs52.7
TONGASS NATIONAL FORESTFederal Excess1.0 yrs52.7
OZ Prince of Wales-HyderGreenfield3.5 yrs52.4
OZ Prince of Wales-HyderGreenfield3.5 yrs51.6
EC FFE Prince of Wales-Hyder Census AreaGreenfield3.5 yrs51.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Smuggler Cove Relay Station, Prince of Wales-Hyder County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.