Skip to content
Gridcensus

Lamar County, Alabama · SERC

DC Readiness
66.5
Good / 100

WEST VERNON is a substation-adjacent datacenter candidate site in Lamar County, Alabama, interconnecting through SERC. It screens at 66.5/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWEST VERNON
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPC Spire Mississippi
IXP distance33.2 mi
Fiber providers5
Fiber coverage100.0%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score55/100

Location context

Nearest datacenterC Spire Mississippi
DC distance33.2 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.46¢/kWh
Industrial electricity6.47¢/kWh
Cooling degree days2,100
Heating degree days2,800
Land price / acre$1,910

Incentive detail: Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
74
Fiber connectivity12%
45
Energy cost10%
50
Water risk8%
92
Natural hazard8%
55
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
20

Nearby comparable sites

Other scored datacenter candidate sites in Lamar County, ranked by DC Readiness.

Sites near WEST VERNON
SiteTypeVoltageCapacityQueue waitScore
CALEDONIASubstation-Adjacent500 kV1,000 MW2.8 yrs63.6
EC Coal Lamar CountyGreenfield3.7 yrs60.6
UNKNOWN112129Substation-Adjacent161 kV100 MW1.0 yrs58.5
TAP141948Substation-Adjacent161 kV100 MW1.0 yrs58.5
UNKNOWN110377Substation-Adjacent161 kV100 MW1.0 yrs58.5
EC Coal Lamar CountyGreenfield3.7 yrs55.7
TAP144771Substation-Adjacent161 kV100 MW2.8 yrs55.6
EC Coal Lamar CountyGreenfield3.7 yrs55.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WEST VERNON, Lamar County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.