Datacenter Sites in Elmore County, Alabama
Elmore County has 59 scored datacenter candidate sites averaging 62.6/100 DC Readiness, with a catalogued aggregate of 4,400 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
59
Candidate sites
62.6/100
Avg DC Readiness
4,400 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Elmore County
Yessales_tax_exemption
Datacenter tax incentive
14.33¢/kWh
Commercial electricity
10.10¢/kWh
Industrial electricity
12
Fiber providers
Low
Water stress
$3,839
Land price / acre
2,100
Cooling degree days
2,800
Heating degree days
63°F
Mean annual temp
Incentive detail: Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.
By site type
Top datacenter sites in Elmore County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| MADISON PARK | Substation-Adjacent | 230 kV | 300 MW | 1.0 yrs | 67.7 |
| UNKNOWN109847 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 65.0 |
| UNKNOWN109217 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.7 |
| UNKNOWN109159 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 63.6 |
| TAP155339 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.9 |
| UNKNOWN109849 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.7 |
| TAP142372 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.6 |
| UNKNOWN110894 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.6 |
| TAP144734 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.4 |
| UNKNOWN110896 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.4 |
| TAP142371 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.2 |
| UNKNOWN109160 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.2 |
| UNKNOWN166910 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.2 |
| TAP144727 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.1 |
| UNKNOWN160837 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.1 |
| UNKNOWN109850 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 62.0 |
| UNKNOWN109211 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 61.9 |
| UNKNOWN109800 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 61.9 |
| UNKNOWN110902 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 61.8 |
| UNKNOWN157350 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 61.8 |
| OZ Elmore | Greenfield | — | — | 3.7 yrs | 60.9 |
| UNKNOWN109835 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.7 |
| TAP146029 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.5 |
| JORDAN DAM | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.4 |
| UNKNOWN158137 | Substation-Adjacent | 115 kV | 100 MW | 1.0 yrs | 60.3 |
Elmore County datacenter FAQ
- How many datacenter sites are in Elmore County?
- 59 scored datacenter candidate sites, averaging 62.6/100 DC Readiness.
- Does Elmore County offer datacenter tax incentives?
- Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.
- What is the natural-hazard risk in Elmore County?
- FEMA's National Risk Index rates Elmore County as "Relatively High" (score 45).
- What are industrial electricity rates in Elmore County?
- Average industrial electricity is 10.10¢/kWh and commercial is 14.33¢/kWh in Elmore County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Elmore County, Alabama. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.