Skip to content
Gridcensus

Clarke County, Alabama · SERC

DC Readiness
53.0
Fair / 100

TAP143426 is a substation-adjacent datacenter candidate site in Clarke County, Alabama, interconnecting through SERC. It screens at 53.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP143426
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPBluBroadband Shell Ave
IXP distance110.0 mi
Fiber providers5
Fiber coverage8.2%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score55/100

Location context

Nearest datacenterBluBroadband Shell Ave
DC distance110.0 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.98¢/kWh
Industrial electricity10.46¢/kWh
Cooling degree days2,100
Heating degree days2,800
Land price / acre$2,688

Incentive detail: Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
74
Fiber connectivity12%
12
Energy cost10%
50
Water risk8%
92
Natural hazard8%
55
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
20

Nearby comparable sites

Other scored datacenter candidate sites in Clarke County, ranked by DC Readiness.

Sites near TAP143426
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN109067Substation-Adjacent230 kV300 MW1.0 yrs59.0
UNKNOWN109172Substation-Adjacent230 kV300 MW1.0 yrs57.4
EC FFE Clarke CountyGreenfield3.7 yrs56.0
EC Coal Clarke CountyGreenfield3.7 yrs54.3
TAP143423Substation-Adjacent115 kV100 MW1.0 yrs53.0
UNKNOWN110457Substation-Adjacent115 kV100 MW1.0 yrs53.0
UNKNOWN109322Substation-Adjacent115 kV100 MW1.0 yrs53.0
TAP143458Substation-Adjacent115 kV100 MW1.0 yrs53.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP143426, Clarke County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.