Pantex Renewable Energy Project (PREP)

Brownfield

Amarillo, Texas

Legacy capacity
12
MW

Pantex Renewable Energy Project (PREP) is a former superfund site in Amarillo, Texas. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 12 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useformer superfund site
Site typeepa_brownfield
Existing capacity12 MW
Acreage16,000 ac

Grid hookup & remediation

Nearest substation0.3 mi
Cleanup statuscleanup_complete
Why this site is datacenter-attractive: a former superfund site of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Get alerts

Track Pantex Renewable Energy Project (PREP)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Nearby datacenter candidate sites

Scored candidate sites near Pantex Renewable Energy Project (PREP), ranked by DC Readiness.

Candidate sites near Pantex Renewable Energy Project (PREP)
SiteTypeStateCountyVoltageCapacityQueue waitScore
POTTER COUNTYSubstation-AdjacentTXPotter County345 kV600 MW1.7 yrs60.5
AJ SWOPESubstation-AdjacentTXPotter County345 kV600 MW1.7 yrs60.1
ROLLING HILLSSubstation-AdjacentTXPotter County230 kV300 MW1.7 yrs58.9
RANDALL COUNTYSubstation-AdjacentTXRandall County230 kV300 MW1.7 yrs58.9
AMARILLO SOUTHSubstation-AdjacentTXRandall County230 kV300 MW1.7 yrs58.9
NICHOLSSubstation-AdjacentTXPotter County230 kV300 MW1.7 yrs58.9
HARRINGTONSubstation-AdjacentTXPotter County230 kV300 MW1.7 yrs58.9
NORTHWESTSubstation-AdjacentTXPotter County230 kV300 MW1.7 yrs58.8

Nearby internet exchanges

See all datacenter sites in Texas →

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

Every site and score for Pantex Renewable Energy Project (PREP), Amarillo, Texas is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.