Conoco

Brownfield

Ponca City, Kay, Oklahoma · Oklahoma Gas & Electric Co

Legacy capacity
66
MW

Conoco is a natural gas plant in Ponca City, Kay, Oklahoma, retired 2006-06-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 66 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usenatural gas plant
Site typeretired_plant
Existing capacity66 MW
Retirement date2006-06-01
EIA plant ID#7185

Grid hookup & remediation

Nearest substation1.4 mi
OperatorOklahoma Gas & Electric Co
Operator address1200 S. Pine St., Ponca City, OK, 74603
Why this site is datacenter-attractive: a natural gas plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Conoco, ranked by DC Readiness.

Candidate sites near Conoco
SiteTypeStateCountyVoltageCapacityQueue waitScore
CHARLES D. LAMB ENERGY CENTERSubstation-AdjacentOKNoble County345 kV600 MW3.4 yrs71.8
SOONERSubstation-AdjacentOKNoble County345 kV600 MW3.4 yrs70.8
CHARLES D. LAMB ENERGY CENTERSubstation-AdjacentOKKay County345 kV600 MW3.5 yrs68.3
FRONTIER WINDPOWERSubstation-AdjacentOKKay County345 kV600 MW3.5 yrs66.6
Greenfield (SOONER - WOODRING)GreenfieldOKNoble County345 kV600 MW3.4 yrs66.1
Greenfield (SOONER - CLEVELAND)GreenfieldOKPawnee County345 kV600 MW3.4 yrs65.8
Greenfield (SOONER - SPRING CREEK)GreenfieldOKNoble County345 kV600 MW3.4 yrs65.7
UNKNOWN119315Substation-AdjacentOKNoble County138 kV100 MW3.4 yrs65.5

See all datacenter sites in Oklahoma

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.