Trenton Diesel

Brownfield

Trenton, Grundy, Missouri · Trenton Municipal Utilities - (MO)

Legacy capacity
4
MW

Trenton Diesel is a oil plant in Trenton, Grundy, Missouri, retired 2011-09-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 4 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useoil plant
Site typeretired_plant
Existing capacity4 MW
Retirement date2011-09-01
EIA plant ID#2163

Grid hookup & remediation

Nearest substation0.1 mi
Operator address1115 W Crowder Rd, Trenton, MO, 64683
Why this site is datacenter-attractive: a oil plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Site conditions & market — Grundy County

County-level intelligence for this site's location — the power economics, water, hazard, connectivity, and workforce a developer screens before ever visiting. Assembled from FEMA NRI, BLS QCEW, FCC BDC, USGS water-use, and EIA.

Market & workforce

Total employment (laborshed)1,959
Construction employment46
Land value$4,305/acre
Datacenter tax incentivesales_tax_exemption

Power economics & interconnection

Commercial power rate10.11¢/kWh
Industrial power rate6.94¢/kWh
Load growth (FERC-714)0.7%

Water & cooling

Water stressLow
Public water supply1.3 MGD
Industrial water use0.0 MGD
Cooling degree days1,500
Mean annual temp56°F

Hazard, flood & connectivity

FEMA risk index38.0 · Relatively High
Fiber providers2 · 96% served

County-level context — address-level utility offerings and flood zoning vary within the county. Confirm site-specific service with the utility and a Phase I ESA.

Nearby brownfield & retired-generation sites

A proximity screen of other retired-plant, contaminated, and EPA-flagged sites near Trenton Diesel — the environmental neighborhood, ranked by legacy grid capacity.

SiteFormer useLegacy MWDistanceCleanup status
Chillicothecoal plant1419.6 mi—
Gallatin #2oil plant420.1 mi—

Derived from GridCensus's retired-generator & EPA brownfield dataset. Not a substitute for an ASTM E1527 Phase I environmental radius report.

Get alerts

Track Trenton Diesel

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Nearby datacenter candidate sites

Scored candidate sites near Trenton Diesel, ranked by DC Readiness.

Candidate sites near Trenton Diesel
SiteTypeStateCountyVoltageCapacityQueue waitScore
EC Near ChillicotheGreenfieldMOLivingston——1.4 yrs59.9
EC Near ChillicotheGreenfieldMOLivingston——1.4 yrs59.2
EC Near Trenton DieselGreenfieldMOGrundy——1.4 yrs58.8
EC Near ChillicotheGreenfieldMOLivingston——1.4 yrs58.6
EC Near Trenton DieselGreenfieldMOGrundy——1.4 yrs58.6
EC Near Trenton DieselGreenfieldMOGrundy——1.4 yrs58.5
EC Near Trenton DieselGreenfieldMOGrundy——1.4 yrs58.3
EC Near ChillicotheGreenfieldMOLivingston——1.4 yrs58.2

See all datacenter sites in Missouri →

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

Every site and score for Trenton Diesel, Trenton, Grundy, Missouri is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.