R D Morrow

Brownfield

Purvis, Lamar, Mississippi · Cooperative Energy

Legacy capacity
400
MW

R D Morrow is a coal plant in Purvis, Lamar, Mississippi, retired 2018-11-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 400 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity400 MW
Retirement date2018-11-01
EIA plant ID#6061

Grid hookup & remediation

Nearest substation1.6 mi
OperatorCooperative Energy
Operator address304 Old Okahola School Road, Purvis, MS, 39475
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near R D Morrow, ranked by DC Readiness.

Candidate sites near R D Morrow
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN112446Substation-AdjacentMSPearl River County230 kV300 MW1.4 yrs67.3
HATTIESBURG SOUTHWESTSubstation-AdjacentMSForrest County230 kV300 MW1.4 yrs66.6
UNKNOWN109927Substation-AdjacentMSLamar County115 kV100 MW1.4 yrs66.2
UNKNOWN110228Substation-AdjacentMSForrest County115 kV100 MW1.4 yrs65.8
UNKNOWN110231Substation-AdjacentMSForrest County161 kV100 MW1.4 yrs65.3
UNKNOWN110240Substation-AdjacentMSStone County115 kV100 MW1.4 yrs65.3
UNKNOWN109941Substation-AdjacentMSForrest County115 kV100 MW1.4 yrs65.3
UNKNOWN109755Substation-AdjacentMSForrest County115 kV100 MW1.4 yrs65.2

See all datacenter sites in Mississippi

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.