Chalk Point Steam

Brownfield

Aquasco, Prince Georges, Maryland · Lanyard Power Holdings, LLC

Legacy capacity
728
MW

Chalk Point Steam is a coal plant in Aquasco, Prince Georges, Maryland, retired 2021-06-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 728 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity728 MW
Retirement date2021-06-01
EIA plant ID#65285

Grid hookup & remediation

Nearest substation0.3 mi
Operator addressP.O. 10, Aquasco, MD, 20608
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Chalk Point Steam, ranked by DC Readiness.

Candidate sites near Chalk Point Steam
SiteTypeStateCountyVoltageCapacityQueue waitScore
BUZZARD POINTSubstation-AdjacentDCDistrict of Columbia230 kV300 MW3.8 yrs68.5
BENNING (230KV)Substation-AdjacentDCDistrict of Columbia230 kV300 MW3.8 yrs68.4
ALABAMA AVENUESubstation-AdjacentDCDistrict of Columbia230 kV300 MW3.8 yrs67.4
BURCHES HILLSubstation-AdjacentMDPrince George's County500 kV1,000 MW3.8 yrs67.1
BLUE PLAINSSubstation-AdjacentDCAlexandria city230 kV300 MW3.8 yrs66.9
OZ District of ColumbiaGreenfieldDCDistrict of Columbia3.1 yrs66.5
EC Coal District of ColumbiaGreenfieldDCDistrict of Columbia3.1 yrs66.4
OZ District of ColumbiaGreenfieldDCDistrict of Columbia3.1 yrs66.3

Nearby internet exchanges

See all datacenter sites in Maryland

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Chalk Point Steam, Aquasco, Prince Georges, Maryland. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.