Bates Mill Upper

Brownfield

Lewiston, Androscoggin, Maine · Lewiston City of

Legacy capacity
4
MW

Bates Mill Upper is a former hydro site in Lewiston, Androscoggin, Maine, retired 2006-09-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 4 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useformer hydro site
Site typeretired_plant
Existing capacity4 MW
Retirement date2006-09-01
EIA plant ID#7044

Grid hookup & remediation

Nearest substation1.9 mi
OperatorLewiston City of
Operator address63 Canal Street (Rear), Lewiston, ME, 4240
Why this site is datacenter-attractive: a former hydro site of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Bates Mill Upper, ranked by DC Readiness.

Candidate sites near Bates Mill Upper
SiteTypeStateCountyVoltageCapacityQueue waitScore
RAVEN FARMSubstation-AdjacentMECumberland County345 kV600 MW3.5 yrs72.8
SURROWIECSubstation-AdjacentMECumberland County345 kV600 MW3.5 yrs72.7
BUXTONSubstation-AdjacentMECumberland County345 kV600 MW3.5 yrs71.6
PRIDES CORNERSubstation-AdjacentMECumberland County115 kV100 MW3.5 yrs67.9
LARRABEE ROADSubstation-AdjacentMEAndroscoggin County345 kV600 MW3.5 yrs67.9
TAP136733Substation-AdjacentMECumberland County115 kV100 MW3.5 yrs66.8
ELM STREETSubstation-AdjacentMECumberland County115 kV100 MW3.5 yrs66.5
Greenfield (SOUTH GORHAM - RAVEN FARM)GreenfieldMECumberland County345 kV600 MW3.5 yrs66.1

Nearby internet exchanges

See all datacenter sites in Maine

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.