Haefling

Brownfield

Lexington, Fayette, Kentucky · Kentucky Utilities Co

Legacy capacity
21
MW

Haefling is a natural gas plant in Lexington, Fayette, Kentucky, retired 2013-12-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 21 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usenatural gas plant
Site typeretired_plant
Existing capacity21 MW
Retirement date2013-12-01
EIA plant ID#1358

Grid hookup & remediation

Nearest substation0.0 mi
Operator address1555 Baumann Dr., Lexington, KY, 40511
Why this site is datacenter-attractive: a natural gas plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Site conditions & market — Fayette County

County-level intelligence for this site's location — the power economics, water, hazard, connectivity, and workforce a developer screens before ever visiting. Assembled from FEMA NRI, BLS QCEW, FCC BDC, USGS water-use, and EIA.

Market & workforce

Total employment (laborshed)159,917
IT / tech employment564
Construction employment10,781
Land value$16,231/acre
Datacenter tax incentivesales_tax_exemption

Power economics & interconnection

Commercial power rate11.76¢/kWh
Industrial power rate7.37¢/kWh
Load growth (FERC-714)0.5%

Water & cooling

Water stressLow
Public water supply35.2 MGD
Industrial water use0.0 MGD
Cooling degree days1,300
Mean annual temp56°F

Hazard, flood & connectivity

FEMA risk index30.0 · Relatively Moderate
Fiber providers5 · 91% served

County-level context — address-level utility offerings and flood zoning vary within the county. Confirm site-specific service with the utility and a Phase I ESA.

Nearby brownfield & retired-generation sites

A proximity screen of other retired-plant, contaminated, and EPA-flagged sites near Haefling — the environmental neighborhood, ranked by legacy grid capacity.

SiteFormer useLegacy MWDistanceCleanup status
E W Browncoal plant29322.7 mi—
Dalecoal plant21619.6 mi—
Tyronecoal plant13718.0 mi—

Derived from GridCensus's retired-generator & EPA brownfield dataset. Not a substitute for an ASTM E1527 Phase I environmental radius report.

Get alerts

Track Haefling

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Nearby datacenter candidate sites

Scored candidate sites near Haefling, ranked by DC Readiness.

Candidate sites near Haefling
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN129961Substation-AdjacentKYFayette County345 kV600 MW3.8 yrs65.5
TAP140103Substation-AdjacentKYWoodford County345 kV600 MW3.8 yrs65.2
BROWN PLANTSubstation-AdjacentKYMercer County345 kV600 MW3.8 yrs65.1
EC Near HaeflingGreenfieldKYFayette——3.6 yrs63.4
HAEFLINGSubstation-AdjacentKYFayette County138 kV100 MW3.8 yrs62.6
UNKNOWN130246Substation-AdjacentKYFayette County138 kV100 MW3.8 yrs61.5
UNKNOWN130278Substation-AdjacentKYFayette County138 kV100 MW3.8 yrs61.5
UNKNOWN130239Substation-AdjacentKYFayette County138 kV100 MW3.8 yrs61.4

Nearby internet exchanges

See all datacenter sites in Kentucky →

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Haefling, Lexington, Fayette, Kentucky. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.