Cameo

Brownfield

Palisade, Mesa, Colorado · Public Service Co of Colorado

Legacy capacity
75
MW

Cameo is a coal plant in Palisade, Mesa, Colorado, retired 2010-12-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 75 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity75 MW
Retirement date2010-12-01
EIA plant ID#468

Grid hookup & remediation

Nearest substation1.5 mi
OperatorPublic Service Co of Colorado
Operator address4 mi E of Palisade on I-70, Palisade, CO, 81526
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Cameo, ranked by DC Readiness.

Candidate sites near Cameo
SiteTypeStateCountyVoltageCapacityQueue waitScore
ADOBESubstation-AdjacentCOMesa County230 kV300 MW1.7 yrs65.6
HORIZONSubstation-AdjacentCOMesa County230 kV300 MW1.7 yrs65.5
GRAND JUNCTIONSubstation-AdjacentCOMesa County345 kV600 MW1.7 yrs65.2
STARKEY GULCHSubstation-AdjacentCOGarfield County230 kV300 MW1.7 yrs64.0
GRAND JUNCTION PSCSubstation-AdjacentCOMesa County230 kV300 MW1.7 yrs62.9
PARACHUTESubstation-AdjacentCOGarfield County230 kV300 MW1.7 yrs62.9
UNKNOWN205920Substation-AdjacentCODelta County115 kV100 MW1.7 yrs62.0
WHEELERSubstation-AdjacentCOGarfield County230 kV300 MW1.7 yrs61.9

See all datacenter sites in Colorado

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Cameo, Palisade, Mesa, Colorado. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.