Barry

Brownfield

Bucks, Mobile, Alabama · Alabama Power Co

Legacy capacity
272
MW

Barry is a coal plant in Bucks, Mobile, Alabama, retired 2015-08-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 272 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usecoal plant
Site typeretired_plant
Existing capacity272 MW
Retirement date2015-08-01
EIA plant ID#3

Grid hookup & remediation

Nearest substation1.1 mi
OperatorAlabama Power Co
Operator addressNorth Highway 43, Bucks, AL, 36512
Why this site is datacenter-attractive: a coal plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Barry, ranked by DC Readiness.

Candidate sites near Barry
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN109076Substation-AdjacentALMobile County230 kV300 MW1.4 yrs70.5
UNKNOWN109130Substation-AdjacentALMobile County230 kV300 MW3.7 yrs69.1
UNKNOWN109085Substation-AdjacentALMobile County230 kV300 MW1.4 yrs68.8
UNKNOWN109065Substation-AdjacentALWashington County230 kV300 MW3.7 yrs68.3
UNKNOWN109320Substation-AdjacentALWashington County230 kV300 MW3.7 yrs68.0
UNKNOWN109319Substation-AdjacentALWashington County230 kV300 MW3.7 yrs67.6
UNKNOWN109061Substation-AdjacentALBaldwin County500 kV1,000 MW3.7 yrs67.4
UNKNOWN109059Substation-AdjacentALMobile County230 kV300 MW3.7 yrs67.1

See all datacenter sites in Alabama

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen