TAP146717

Substation

Virginia

Max voltage
115
kV

TAP146717 is an electric transmission substation in Virginia. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

Operator not catalogued for this substation.

Coordinates37.0990, -79.2558

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#5311115 kVIN SERVICE3.5 mi
#5481115 kVIN SERVICE0.5 mi
#46151115 kVIN SERVICE0.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP146717, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP146717 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
JOSHUA FALLSSubstation-AdjacentVALynchburg city765 kV1,000 MW3.0 yrs73.3
Greenfield (CLOVERDALE 765KV - JOSHUA FALL)GreenfieldVALynchburg city765 kV1,000 MW3.0 yrs71.1
Greenfield (CLOVERDALE 765KV - JOSHUA FALL)GreenfieldVABedford County765 kV1,000 MW3.0 yrs71.0
Multitrade of Pittsylvania LPBrownfieldVACampbell90 MW70.8
Greenfield (CLOVERDALE 765KV - JOSHUA FALL)GreenfieldVABedford County765 kV1,000 MW3.0 yrs70.5
REUSENSSubstation-AdjacentVALynchburg city138 kV100 MW3.0 yrs69.6
HALIFAXSubstation-AdjacentVAHalifax County230 kV300 MW3.1 yrs69.4
SMITH MOUNTAINSubstation-AdjacentVALynchburg city138 kV100 MW3.0 yrs69.3

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP146717 substation, Virginia. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.