NORTHSIDE

Substation

Georgia · JEA

Max voltage
230
kV

NORTHSIDE is an electric transmission substation in Georgia, operated by JEA. It is classified as high-voltage (230 kv) and connects 11 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage138 kV
Voltage classHigh-voltage (230 kV)
Connected lines11

Ownership & operation

OperatorJEA
StateGeorgia
Coordinates30.4038, -81.5696

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#64516230 kVJEA0.2 mi
#45224230 kVJEAIN SERVICE28.0 mi
#47729230 kVJEAIN SERVICE6.6 mi
#47833230 kVJEAIN SERVICE1.4 mi
#2468230 kVJEAIN SERVICE11.1 mi
#39101230 kVJEAIN SERVICE28.9 mi
#43226230 kVJEAIN SERVICE1.9 mi
#8188138 kVJEAIN SERVICE13.8 mi
#33460138 kVJEAIN SERVICE6.6 mi
#36204138 kVJEAIN SERVICE10.6 mi
#43735138 kVJEAIN SERVICE0.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of NORTHSIDE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near NORTHSIDE substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BARTRAMSubstation-AdjacentFLDuval County230 kV300 MW3.6 yrs75.6
SWITZERLANDSubstation-AdjacentFLClay County230 kV300 MW3.6 yrs75.2
UNKNOWN120521Substation-AdjacentFLDuval County230 kV300 MW3.6 yrs75.0
UNKNOWN120554Substation-AdjacentFLDuval County230 kV300 MW5.8 yrs74.1
UNKNOWN120519Substation-AdjacentFLDuval County230 kV300 MW3.6 yrs74.1
FORT CAROLINESubstation-AdjacentFLDuval County230 kV300 MW5.8 yrs73.5
NAVAL SUBMARINE BASE KINGS BAYSubstation-AdjacentGACamden County230 kV300 MW5.8 yrs73.4
TAP161532Substation-AdjacentFLDuval County230 kV300 MW3.6 yrs73.2

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.