Duval, Florida · SERC

DC Readiness
75.6
Excellent / 100

BARTRAM is a substation-adjacent datacenter candidate site in Duval, Florida, interconnecting through SERC. It screens at 75.6/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBARTRAM
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.6 yrs
Recent queue wait3.3 yrs
Completion rate26%
Withdrawal rate74%

Connectivity

Nearest IXPTierPoint Jacksonville
IXP distance6.8 mi
Fiber providers18
Fiber coverage72.7%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance230.2 mi

Site characteristics

Parcel ownerJEA
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)1.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index93.5 (avg 100)

Location context

Nearest datacenterTierPoint Jacksonville
DC distance6.8 mi
Nearest rail1.0 mi
Nearest gas pipeline3.9 mi
Nearest fiber route118.2 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.97¢/kWh
Industrial electricity7.84¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$13,486

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
75
Fiber connectivity12%
88
Energy cost10%
89
Water risk8%
84
Natural hazard8%
45
Buildability7%
95
Labor market4%
50
DC cluster4%
80
Land / acreage3%
41
Construction cost3%
72
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Duval, ranked by DC Readiness.

Sites near BARTRAM
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN120521Substation-Adjacent230 kV300 MW3.6 yrs75.0
UNKNOWN120554Substation-Adjacent230 kV300 MW5.8 yrs74.1
UNKNOWN120519Substation-Adjacent230 kV300 MW3.6 yrs74.1
FORT CAROLINESubstation-Adjacent230 kV300 MW5.8 yrs73.5
TAP161532Substation-Adjacent230 kV300 MW3.6 yrs73.2
BLOUNT ISLANDSubstation-Adjacent230 kV300 MW5.8 yrs73.2
TAP151528Substation-Adjacent230 kV300 MW3.6 yrs72.7
UNKNOWN120554Substation-Adjacent230 kV300 MW3.6 yrs72.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for BARTRAM, Duval. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.