Greenfield (TONGUE RIVER - UNKNOWN201476)

Greenfield

Sheridan County, Wyoming · WECC

DC Readiness
65.1
Good / 100

Greenfield (TONGUE RIVER - UNKNOWN201476) is a greenfield datacenter candidate site in Sheridan County, Wyoming, interconnecting through WECC. It screens at 65.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTONGUE RIVER
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPACT Sheridan
IXP distance15.5 mi
Fiber providers6
Fiber coverage57.7%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance390.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerBASIN ELECTRIC POWER COOP
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)2.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score90/100
Construction cost index74.7 (avg 100)

Location context

Nearest datacenterACT Sheridan
DC distance15.5 mi
Nearest rail4.1 mi
Nearest gas pipeline3.7 mi
Nearest fiber route71.4 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity10.99¢/kWh
Industrial electricity8.57¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$1,582

Incentive detail: No state corporate or personal income tax; low property taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
31
Fiber connectivity12%
76
Energy cost10%
94
Water risk8%
58
Natural hazard8%
90
Buildability7%
70
Labor market4%
50
DC cluster4%
80
Land / acreage3%
53
Construction cost3%
88
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Sheridan County, ranked by DC Readiness.

Sites near Greenfield (TONGUE RIVER - UNKNOWN201476)
SiteTypeVoltageCapacityQueue waitScore
DECKERSubstation-Adjacent230 kV300 MW1.1 yrs76.0
TAP209945Substation-Adjacent230 kV300 MW1.1 yrs75.8
TAP209947Substation-Adjacent230 kV300 MW1.1 yrs75.5
TAP209946Substation-Adjacent230 kV300 MW1.1 yrs74.7
TAP209950Substation-Adjacent230 kV300 MW1.1 yrs73.9
TAP205618Substation-Adjacent230 kV300 MW1.7 yrs73.3
TONGUE RIVERSubstation-Adjacent230 kV300 MW1.7 yrs71.7
Greenfield (DECKER - UNKNOWN202499)Greenfield230 kV300 MW1.1 yrs70.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (TONGUE RIVER - UNKNOWN201476), Sheridan County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.