Greenfield (UNKNOWN129869 - KING PLANT)

Greenfield

Pierce County, Wisconsin · MISO

DC Readiness
65.9
Good / 100

Greenfield (UNKNOWN129869 - KING PLANT) is a greenfield datacenter candidate site in Pierce County, Wisconsin, interconnecting through MISO. It screens at 65.9/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN129869
Substation voltage345 kV
Available capacity600 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPDataBank Minneapolis (MSP2)
IXP distance31.4 mi
Fiber providers10
Fiber coverage63.0%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance206.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerNORTHERN STATES POWER CO - WISCONSIN
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score63/100
Construction cost index86.6 (avg 100)

Location context

Nearest datacenterDatacenter 1454573842
DC distance28.3 mi
Nearest rail9.6 mi
Nearest gas pipeline2.1 mi
Nearest fiber route197.4 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.60¢/kWh
Industrial electricity8.60¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$5,863

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
57
Fiber connectivity12%
61
Energy cost10%
86
Water risk8%
94
Natural hazard8%
63
Buildability7%
45
Labor market4%
50
DC cluster4%
60
Land / acreage3%
46
Construction cost3%
78
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Pierce County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN129869 - KING PLANT)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN157189Substation-Adjacent161 kV100 MW1.4 yrs68.7
Greenfield (UNKNOWN129869 - KING PLANT)Greenfield345 kV600 MW1.4 yrs66.9
TAP143562Substation-Adjacent115 kV100 MW1.4 yrs63.8
Greenfield (ALMA - UNKNOWN131982)Greenfield161 kV100 MW1.4 yrs63.0
Greenfield (UNKNOWN131981 - UNKNOWN131982)Greenfield161 kV100 MW1.4 yrs62.6
Greenfield (UNKNOWN129869 - KING PLANT)Greenfield345 kV600 MW1.4 yrs62.4
Greenfield (UNKNOWN131981 - UNKNOWN163358)Greenfield161 kV100 MW1.4 yrs59.8
OZ PierceGreenfield1.4 yrs59.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN129869 - KING PLANT), Pierce County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.