Greenfield (SOUTH FOND DE LAC - EDGEWATER )

Greenfield

Fond du Lac County, Wisconsin · MISO

DC Readiness
59.3
Good / 100

Greenfield (SOUTH FOND DE LAC - EDGEWATER ) is a greenfield datacenter candidate site in Fond du Lac County, Wisconsin, interconnecting through MISO. It screens at 59.3/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSOUTH FOND DE LAC
Substation voltage345 kV
Available capacity600 MW
LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth41
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPEthoplex Edge DC - Fond du Lac
IXP distance19.9 mi
Fiber providers4
Fiber coverage38.6%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance129.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerState Of Wisconsin Dept Of Nat Resources
Land owner typeprivate
Buildability20.0/100
Land cover (NLCD)Emergent Herbaceous Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index105.2 (avg 100)

Location context

Nearest datacenterEthoplex Edge DC - Fond du Lac
DC distance19.9 mi
Nearest rail7.9 mi
Nearest gas pipeline3.8 mi
Nearest fiber route54.6 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.68¢/kWh
Industrial electricity8.70¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$7,870

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
47
Fiber connectivity12%
30
Energy cost10%
84
Water risk8%
91
Natural hazard8%
78
Buildability7%
20
Labor market4%
50
DC cluster4%
65
Land / acreage3%
42
Construction cost3%
62
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Fond du Lac County, ranked by DC Readiness.

Sites near Greenfield (SOUTH FOND DE LAC - EDGEWATER )
SiteTypeVoltageCapacityQueue waitScore
MARTIN ROADSubstation-Adjacent138 kV100 MW1.4 yrs72.0
SOUTH FOND DE LACSubstation-Adjacent345 kV600 MW1.4 yrs70.5
RIENZISubstation-Adjacent138 kV100 MW1.4 yrs69.2
Greenfield (SOUTH FOND DE LAC - FITZGERALD)Greenfield345 kV600 MW1.4 yrs69.0
NORTH FOND DU LACSubstation-Adjacent138 kV100 MW1.4 yrs68.7
Greenfield (TAP138062 - CYPRESS)Greenfield345 kV600 MW1.4 yrs68.5
FORWARD ENERGY CENTERSubstation-Adjacent138 kV100 MW1.4 yrs68.4
KETTLE MORRAINESubstation-Adjacent138 kV100 MW1.4 yrs67.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (SOUTH FOND DE LAC - EDGEWATER ), Fond du Lac County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.