Greenfield (HAPPY VALLEY - PORT ANGELES)

Greenfield

Jefferson County, Washington · WECC

DC Readiness
58.1
Good / 100

Greenfield (HAPPY VALLEY - PORT ANGELES) is a greenfield datacenter candidate site in Jefferson County, Washington, interconnecting through WECC. It screens at 58.1/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHAPPY VALLEY
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPDigital Fortress (LYN)
IXP distance46.7 mi
Fiber providers6
Fiber coverage9.8%
Nearest cloud providerAzure
Nearest cloud regionwestus2
Cloud region distance167.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerPUD NO 1 OF CLALLAM COUNTY
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)1.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index73.3 (avg 100)

Location context

Nearest datacenterCentersquare Lynnwood SE1
DC distance45.8 mi
Nearest rail2.4 mi
Nearest gas pipeline40.5 mi
Nearest fiber route25.9 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.74¢/kWh
Industrial electricity6.84¢/kWh
Cooling degree days300
Heating degree days5,000
Land price / acre$13,294

Incentive detail: Sales tax exemption on DC equipment and construction for eligible facilities; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
33
Fiber connectivity12%
43
Energy cost10%
97
Water risk8%
72
Natural hazard8%
72
Buildability7%
70
Labor market4%
50
DC cluster4%
45
Land / acreage3%
48
Construction cost3%
89
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Jefferson County, ranked by DC Readiness.

Sites near Greenfield (HAPPY VALLEY - PORT ANGELES)
SiteTypeVoltageCapacityQueue waitScore
TAP207138Substation-Adjacent115 kV100 MW1.7 yrs60.4
UNKNOWN207137Substation-Adjacent115 kV100 MW1.7 yrs60.3
TAP207140Substation-Adjacent115 kV100 MW1.7 yrs60.0
Greenfield (FAIRMOUNT - PORT ANGELES)Greenfield230 kV300 MW1.7 yrs55.9
OZ JeffersonGreenfield1.7 yrs53.8
OZ JeffersonGreenfield1.7 yrs46.6
Glines Hydroelectric ProjectBrownfield16 MW1.7 yrs41.7
Mine SiteFormer Mine41.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.