Greenfield (TAP207481 - UNKNOWN207483)

Greenfield

Sevier County, Utah · WECC

DC Readiness
55.2
Good / 100

Greenfield (TAP207481 - UNKNOWN207483) is a greenfield datacenter candidate site in Sevier County, Utah, interconnecting through WECC. It screens at 55.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP207481
Substation voltage138 kV
Available capacity100 MW
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPVoonami SLC1
IXP distance88.9 mi
Fiber providers6
Fiber coverage52.4%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance118.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerPACIFICORP
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index56.3 (avg 100)

Location context

Nearest datacenterMeta Eagle Mountain Data Center
DC distance85.0 mi
Nearest rail1.3 mi
Nearest gas pipeline22.9 mi
Nearest fiber route123.8 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.54¢/kWh
Industrial electricity7.61¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$5,351

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
34
Fiber connectivity12%
65
Energy cost10%
96
Water risk8%
24
Natural hazard8%
85
Buildability7%
92
Labor market4%
50
DC cluster4%
25
Land / acreage3%
47
Construction cost3%
100
Gas pipeline2%
26
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Sevier County, ranked by DC Readiness.

Sites near Greenfield (TAP207481 - UNKNOWN207483)
SiteTypeVoltageCapacityQueue waitScore
TAP207480Substation-Adjacent138 kV100 MW1.7 yrs64.1
SIGURDSubstation-Adjacent345 kV600 MW1.7 yrs63.3
UNKNOWN202233Substation-Adjacent115 kV100 MW1.7 yrs63.2
RICHFIELDSubstation-Adjacent138 kV100 MW1.7 yrs63.0
Greenfield (EMERY - SIGURD)Greenfield345 kV600 MW1.7 yrs61.7
UNKNOWN207475Substation-Adjacent138 kV100 MW1.7 yrs61.6
Greenfield (SIGURD - RED BUTTE)Greenfield345 kV600 MW1.7 yrs61.6
Greenfield (CLOVER - SIGURD)Greenfield345 kV600 MW1.7 yrs61.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (TAP207481 - UNKNOWN207483), Sevier County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.