Greenfield (JOHN DAY 2 - GRIZZLY) is a greenfield datacenter candidate site in Sherman County, Oregon, interconnecting through WECC. It screens at 65.5/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationJOHN DAY 2
Substation voltage500 kV
Available capacity1,000 MW
Utility commercial rate0.06¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPGRHMORXB - Gresham Central Office
IXP distance77.4 mi
Fiber providers4
Fiber coverage41.3%
Nearest cloud providerAWS
Nearest cloud regionus-west-2
Cloud region distance64.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerBONNEVILLE POWER ADMINISTRATION
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index123.1 (avg 100)

Location context

Nearest datacenterGoogle The Dalles 2
DC distance19.5 mi
Nearest rail1.5 mi
Nearest gas pipeline18.1 mi
Nearest fiber route63.4 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity5.79¢/kWh
Industrial electricity7.05¢/kWh
Cooling degree days300
Heating degree days4,700
Land price / acre$1,410

Incentive detail: Enterprise Zone property tax exemption for 3-15 years; no sales tax in Oregon.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
32
Fiber connectivity12%
61
Energy cost10%
94
Water risk8%
63
Natural hazard8%
78
Buildability7%
80
Labor market4%
50
DC cluster4%
70
Land / acreage3%
53
Construction cost3%
47
Gas pipeline2%
42
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Sherman County, ranked by DC Readiness.

Sites near Greenfield (JOHN DAY 2 - GRIZZLY)
SiteTypeVoltageCapacityQueue waitScore
HAY CANYONSubstation-Adjacent345 kV600 MW1.7 yrs67.4
JONES CANYONSubstation-Adjacent230 kV300 MW1.7 yrs66.4
Greenfield (BUCKLEY - SLATT)Greenfield500 kV1,000 MW1.7 yrs66.3
KLONDIKE WINDPOWER III PHASE 1Substation-Adjacent230 kV300 MW1.7 yrs66.2
KLONDIKE SCHOOLHOUSESubstation-Adjacent230 kV300 MW1.7 yrs66.0
KLONDIKE WINDPOWER IISubstation-Adjacent230 kV300 MW1.7 yrs65.9
Greenfield (JOHN DAY 2 - GRIZZLY)Greenfield500 kV1,000 MW1.7 yrs65.8
Greenfield (JOHN DAY 2 - MARION)Greenfield500 kV1,000 MW1.7 yrs65.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (JOHN DAY 2 - GRIZZLY), Sherman County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.