Greenfield (UNKNOWN205315 - TAP205316)

Greenfield

Harney County, Oregon · WECC

DC Readiness
49.3
Fair / 100

Greenfield (UNKNOWN205315 - TAP205316) is a greenfield datacenter candidate site in Harney County, Oregon, interconnecting through WECC. It screens at 49.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN205315
Substation voltage115 kV
Available capacity100 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPTonaquint Data Center - Boise ID
IXP distance147.0 mi
Fiber providers5
Fiber coverage2.4%
Nearest cloud providerAWS
Nearest cloud regionus-west-2
Cloud region distance252.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerHARNEY ELECTRIC COOP, INC
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index101.7 (avg 100)

Location context

Nearest datacenterApple Prineville
DC distance138.6 mi
Nearest rail2.5 mi
Nearest gas pipeline8.5 mi
Nearest fiber route61.0 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.30¢/kWh
Industrial electricity7.69¢/kWh
Cooling degree days300
Heating degree days4,700
Land price / acre$1,268

Incentive detail: Enterprise Zone property tax exemption for 3-15 years; no sales tax in Oregon.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
32
Fiber connectivity12%
8
Energy cost10%
94
Water risk8%
60
Natural hazard8%
78
Buildability7%
80
Labor market4%
50
DC cluster4%
20
Land / acreage3%
54
Construction cost3%
65
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Harney County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN205315 - TAP205316)
SiteTypeVoltageCapacityQueue waitScore
BURNSSubstation-Adjacent500 kV1,000 MW1.7 yrs61.7
Greenfield (BURNS - HEMINGWAY)Greenfield500 kV1,000 MW1.7 yrs57.8
Greenfield (BURNS - HEMINGWAY)Greenfield500 kV1,000 MW1.7 yrs57.3
Greenfield (BURNS - HEMINGWAY)Greenfield500 kV1,000 MW1.7 yrs57.2
Greenfield (BURNS - HEMINGWAY)Greenfield500 kV1,000 MW1.7 yrs57.2
Greenfield (SUMMER LAKE - BURNS)Greenfield500 kV1,000 MW1.7 yrs56.5
Greenfield (SUMMER LAKE - BURNS)Greenfield500 kV1,000 MW1.7 yrs56.4
Greenfield (SUMMER LAKE - BURNS)Greenfield500 kV1,000 MW1.7 yrs55.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN205315 - TAP205316), Harney County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.