Greenfield (GRAND FORKS - CENTER 345KV SWI) is a greenfield datacenter candidate site in Griggs County, North Dakota, interconnecting through SPP. It screens at 69.3/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationGRAND FORKS
Substation voltage345 kV
Available capacity600 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth9
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPMidco Grand Forks
IXP distance57.0 mi
Fiber providers5
Fiber coverage100.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance452.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerSlaubaugh, Ronald W. & Dorothy A.
Parcel APN10347000
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)1.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score80/100
Construction cost index43.6 (avg 100)

Location context

Nearest datacenterMidco Grand Forks
DC distance57.0 mi
Nearest rail11.1 mi
Nearest gas pipeline26.7 mi
Nearest fiber route4.9 mi
County hazard (FEMA NRI)Relatively Low (20)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.10¢/kWh
Industrial electricity8.16¢/kWh
Cooling degree days500
Heating degree days8,600
Land price / acre$2,118

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
66
Fiber connectivity12%
72
Energy cost10%
92
Water risk8%
79
Natural hazard8%
80
Buildability7%
65
Labor market4%
50
DC cluster4%
40
Land / acreage3%
52
Construction cost3%
100
Gas pipeline2%
14
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Griggs County, ranked by DC Readiness.

Sites near Greenfield (GRAND FORKS - CENTER 345KV SWI)
SiteTypeVoltageCapacityQueue waitScore
TAP134573Substation-Adjacent230 kV300 MW1.4 yrs73.2
Greenfield (GRAND FORKS - CENTER 345KV SWI)Greenfield345 kV600 MW1.4 yrs71.3
Greenfield (GRAND FORKS - CENTER 345KV SWI)Greenfield345 kV600 MW1.4 yrs70.0
Greenfield (GRAND FORKS - CENTER 345KV SWI)Greenfield345 kV600 MW1.4 yrs69.7
Greenfield (TAP134573 - JAMESTOWN)Greenfield230 kV300 MW1.4 yrs68.1
Greenfield (TAP134573 - JAMESTOWN)Greenfield230 kV300 MW1.4 yrs67.9
Greenfield (TAP134573 - JAMESTOWN)Greenfield230 kV300 MW1.4 yrs67.7
Greenfield (TAP134573 - JAMESTOWN)Greenfield230 kV300 MW1.4 yrs67.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (GRAND FORKS - CENTER 345KV SWI), Griggs County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.