Greenfield (AMBROSIA - WEST MESA)

Greenfield

Cibola County, New Mexico · SPP

DC Readiness
58.0
Good / 100

Greenfield (AMBROSIA - WEST MESA) is a greenfield datacenter candidate site in Cibola County, New Mexico, interconnecting through SPP. It screens at 58.0/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationAMBROSIA
Substation voltage230 kV
Available capacity300 MW
LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPOso Grande Technologies
IXP distance58.8 mi
Fiber providers3
Fiber coverage58.3%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance285.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerNAVAJO TRIBAL UTILITY AUTHORITY
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)4.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index65.0 (avg 100)

Location context

Nearest datacenterOso Grande
DC distance58.8 mi
Nearest rail7.7 mi
Nearest gas pipeline8.3 mi
Nearest fiber route59.4 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity13.32¢/kWh
Industrial electricity7.93¢/kWh
Cooling degree days1,400
Heating degree days4,000
Land price / acre$406

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
47
Fiber connectivity12%
60
Energy cost10%
90
Water risk8%
30
Natural hazard8%
85
Buildability7%
70
Labor market4%
50
DC cluster4%
40
Land / acreage3%
55
Construction cost3%
96
Gas pipeline2%
73
Tax incentive2%
0
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in Cibola County, ranked by DC Readiness.

Sites near Greenfield (AMBROSIA - WEST MESA)
SiteTypeVoltageCapacityQueue waitScore
BLUE WATERSubstation-Adjacent115 kV100 MW3.5 yrs60.9
TAP318063Substation-Adjacent115 kV100 MW3.5 yrs60.3
Greenfield (TAP318062 - LOST HORIZON TAP)Greenfield115 kV100 MW3.5 yrs56.5
Greenfield (TAP318062 - LOST HORIZON TAP)Greenfield115 kV100 MW3.5 yrs55.4
Greenfield (AMBROSIA - WEST MESA)Greenfield230 kV300 MW3.5 yrs55.4
OZ CibolaGreenfield3.5 yrs54.7
Greenfield (TAP318063 - None)Greenfield115 kV100 MW3.5 yrs54.0
Greenfield (TAP318062 - LOST HORIZON TAP)Greenfield115 kV100 MW3.5 yrs53.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.