Greenfield (GONDER - MACHACEK)

Greenfield

White Pine County, Nevada · WECC

DC Readiness
50.7
Fair / 100

Greenfield (GONDER - MACHACEK) is a greenfield datacenter candidate site in White Pine County, Nevada, interconnecting through WECC. It screens at 50.7/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 5.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationGONDER
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait5.8 yrs
Recent queue wait5.8 yrs
Completion rate10%
Withdrawal rate90%

Connectivity

Fiber providers2
Fiber coverage1.2%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance204.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerMT. WHEELER POWER
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone D
Water stress (WRI)4.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score88/100
Construction cost index105.8 (avg 100)

Location context

Nearest rail5.8 mi
Nearest gas pipeline98.0 mi
Nearest fiber route29.1 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (sales_tax_abatement)
Commercial electricity9.57¢/kWh
Industrial electricity6.96¢/kWh
Cooling degree days2,000
Heating degree days3,700
Land price / acre$1,791

Incentive detail: Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
31
Fiber connectivity12%
46
Energy cost10%
95
Water risk8%
9
Natural hazard8%
88
Buildability7%
70
Labor market4%
50
DC cluster4%
10
Land / acreage3%
53
Construction cost3%
62
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
25

Nearby comparable sites

Other scored datacenter candidate sites in White Pine County, ranked by DC Readiness.

Sites near Greenfield (GONDER - MACHACEK)
SiteTypeVoltageCapacityQueue waitScore
ROBINSONSubstation-Adjacent500 kV1,000 MW5.8 yrs61.2
GONDERSubstation-Adjacent345 kV600 MW5.8 yrs59.1
Ely Energy CenterBrownfield345 kV1,500 MW5.8 yrs56.9
OSCEOLASubstation-Adjacent230 kV300 MW5.8 yrs56.8
Greenfield (TAP307893 - ROBINSON)Greenfield500 kV1,000 MW5.8 yrs55.9
Greenfield (TAP307893 - ROBINSON)Greenfield500 kV1,000 MW5.8 yrs54.7
Greenfield (ROBINSON - FALCON)Greenfield345 kV600 MW5.8 yrs54.3
Greenfield (ROBINSON - FALCON)Greenfield345 kV600 MW5.8 yrs53.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.