Greenfield (BROADVIEW - JUDITH GAP WIND FA)

Greenfield

Golden Valley County, Montana · SPP

DC Readiness
63.6
Good / 100

Greenfield (BROADVIEW - JUDITH GAP WIND FA) is a greenfield datacenter candidate site in Golden Valley County, Montana, interconnecting through SPP. It screens at 63.6/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBROADVIEW
Substation voltage230 kV
Available capacity300 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPParsec
IXP distance59.2 mi
Fiber providers3
Fiber coverage85.6%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance404.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerMccormick William A
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score88/100
Construction cost index86.6 (avg 100)

Location context

Nearest datacenterParsec Data Management
DC distance59.2 mi
Nearest rail6.5 mi
Nearest gas pipeline8.5 mi
Nearest fiber route154.0 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity8.42¢/kWh
Industrial electricity8.61¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$977

Incentive detail: New/expanding industry tax abatement available for DC construction.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
74
Fiber connectivity12%
28
Energy cost10%
90
Water risk8%
56
Natural hazard8%
88
Buildability7%
80
Labor market4%
50
DC cluster4%
40
Land / acreage3%
54
Construction cost3%
78
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Golden Valley County, ranked by DC Readiness.

Sites near Greenfield (BROADVIEW - JUDITH GAP WIND FA)
SiteTypeVoltageCapacityQueue waitScore
BROADVIEWSubstation-Adjacent500 kV1,000 MW1.1 yrs80.1
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs73.9
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs72.6
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs71.6
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs71.6
Greenfield (BROADVIEW - GARRISON)Greenfield500 kV1,000 MW1.1 yrs70.4
TAP204180Substation-Adjacent115 kV100 MW1.1 yrs69.6
UNKNOWN209912Substation-Adjacent115 kV100 MW1.1 yrs69.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (BROADVIEW - JUDITH GAP WIND FA), Golden Valley County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.