Sub 3 Generating Station

Brownfield

Macon, Missouri · MISO

DC Readiness
53.9
Fair / 100

Sub 3 Generating Station is a brownfield datacenter candidate site in Macon, Missouri, interconnecting through MISO. It screens at 53.9/100 DC Readiness with a catalogued 7 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Available capacity7 MW
LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth34
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPLightEdge Kansas City Subtropolis (KCI1)
IXP distance115.4 mi
Fiber providers5
Fiber coverage87.2%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance150.1 mi

Site characteristics

Site typeBrownfield
Parcel ownerCity of Macon
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity
Former useoil
Existing capacity7 MW
Retirement date2023-05-01

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteLONGBRANCH AUTO BODY
Hazard sub-score52/100
Construction cost index55.1 (avg 100)

Location context

Nearest datacenterCarfax
DC distance58.6 mi
Nearest rail1.9 mi
Nearest gas pipeline6.6 mi
Nearest fiber route86.3 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.45¢/kWh
Industrial electricity7.23¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$4,026

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
23
Speed to power15%
39
Fiber connectivity12%
30
Energy cost10%
91
Water risk8%
88
Natural hazard8%
52
Buildability7%
92
Labor market4%
50
DC cluster4%
45
Land / acreage3%
58
Construction cost3%
100
Gas pipeline2%
79
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Macon, ranked by DC Readiness.

Sites near Sub 3 Generating Station
SiteTypeVoltageCapacityQueue waitScore
Greenfield (UNKNOWN117964 - THOMAS HILL)Greenfield161 kV100 MW1.4 yrs60.4
Greenfield (UNKNOWN117964 - THOMAS HILL)Greenfield161 kV100 MW1.4 yrs60.4
Greenfield (UNKNOWN117964 - THOMAS HILL)Greenfield161 kV100 MW1.4 yrs59.7
EC Near Sub 2 Generating StationGreenfield1.4 yrs59.5
MaconBrownfield10 MW1.4 yrs59.3
EC Near La PlataGreenfield1.4 yrs58.4
EC Near Sub 2 Generating StationGreenfield1.4 yrs58.3
EC Near MaconGreenfield1.4 yrs57.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.